No. 110/2011
From 9/19/2011 
Until 9/27/2011 

Rotterdam OudeMaas Botlekbrug 

Work under the fixed bridge sections

1. From Monday 19 September 2011 until Friday 23 September 2011, and from Monday 26 September 2011 until Tuesday 27 September 2011, inspection work will be carried out at various points under the fixed sections of the Botlekbrug. The work in question, which will involve the use of an hydraulic platform and/or a working vessel, will take place from 07:30 to 16:30.

2. Shipping must make allowance for the fact that, as a result of this work, the fixed-bridge-section navigation opening in question will be narrowed.

3. Further information can be obtained by contacting:
- Traffic Center Rotterdam, the Traffic Flow Management duty officer,
telephone number +31-(0)10 - 2522601 or VHF channel 11;
- Harbour Coordination Center, the HCC duty officer,
telephone number +31-(0)10-2522400 or VHF channel 19.

 ROTTERDAM HARBOUR MASTER
 and State Harbour Master for the Rotterdam–Rijnmond region
 23 August 2011