Porthos does not expect any delays due to provisional advice EIA Commission
In its provisional advice, the Commission for Environmental Impact Assessment (EIA) has indicated that it is of the opinion that several points of the EIA for Porthos are incomplete. Porthos is the Rotterdam project for CO2 transport and storage. The Porthos project organisation and the Ministry of Economic Affairs and Climate have promised the EIA Commission to submit supplementary information within two weeks, which the Commission can include in its final assessment of the EIA. Given the subjects concerned, the project organisation does not expect any consequences for the progress of the project.